Click here to return to the home page
Our History
What do we do?
How do we do it?
How much does it cost?
Pitfalls
Previous projects
Standards and Regulations
How do we match your requirements?
Statutory and non-statutory requirements
 


Pitfalls

So, why not save circa 10% of the cost and just arrange it all yourself (assuming that your time costs less) – or just leave it to the contractors?

If you have the spare time, understand what is required, are willing to take the technical and HSE responsibility, and more – then fine. However, below are but a few of the instances we have come across, where our experience would have prevented a problem - that is not always easy to spot – even by the professionals!

We are not publishing the solutions, but will reveal them to our clients - and ensure that they do not join the list!

Mechanical Services
Forever blowing bubbles!
The central plant air handling unit stands alongside the computer room in a separate purpose built plenum plant room. The plant room is just that – a double skin block work wall on a concrete slab and with a concrete slab roof. The walls are painted with emulsion paint in an attempt to hide its ghastly appearance.

Conditioned air is ducted into the computer room floor void and returns at high level from the computer room suspended ceiling void – back into the plant room. From the room it is sucked back through the air conditioner for reconditioning and recycling. This is the standard arrangement for plenum plant rooms.

When turned on the air conditioning however, cannot control conditions within the computer room. Engineers and manufacturers are called in. Calculations are repeated and the equipment is checked out – all is found to be correct.

The commissioning engineer has an idea and asks for a bucket of very soapy water. He exits the plant room and then throws the soapy water at a wall of the plant room. The side of the plant room disappears in a cloud of bubbles!

To find out what it’s all about and how to avoid – appoint CCS

Frying tonight!
The computer room equipment is left running overnight. Other than the security guards the facility is empty. There is a break in the mains power. The UPS seamlessly supports the computer equipment for the few minutes until the standby generator kicks in and takes over. The UPS doesn’t need to support the air conditioning because the room temperature will not rise critically during the few minutes it takes for the generator to start – and anyway the UPS can only support the load for 10 minutes if the mains or generator don’t provide power.
The computer equipment not fitted with high temperature isolation, fries!
To find out what it’s all about and how to avoid – appoint CCS

Barafoam Hotel
The duct sections delivered to site to provide supply and return the air to the computer room on the floor above are circa 1.2m x 2.4m x 2m tall. They are laid on their sides and are lined with a thick layer of non-combustible acoustic foam. The duct erectors are from the South, working on site and staying overnight in B&B. The premises caretaker secures the site at night.

The foam is a relatively new product that was developed for, and is used in airliner construction – meeting CAA specifications regarding combustibility.

The computer room is for a City Council in the North. An association of half a dozen underwriters, based in London, is underwriting the insurance risk.

The largest of the underwriting companies expresses concern/interest in the claim that the foam does not support combustion and sends a surveyor to site to obtain a sample of the foam from the ducting.

A sample is taken, placed in a plastic container to avoid pollution and returned to the London office. The surveyor takes the sample to the chairman’s office. The chairman places the sample in an ashtray on the Board meeting table, strikes a match and offers it to the foam.
The chairman and surveyor are seen running from the office, pursued by a large black plume of noxious smoke!

The insurers specification requirements are immediately upgraded to require that automatic gas flooding protect the duct lining. The manufacturers of the foam are called in to answer and the insurers advise their industry of a possible hazard to all aircraft lined with this product!

An electron microscopic investigation reveals that some of the foam linings are polluted with wool and nylon fibres. These are acting as a catalyst to promote combustion.
Where would such fibres – to just some of the linings, have come from?
To find out what it’s all about and how to avoid – appoint CCS

Standby capacity?
A client didn’t think this up, but did a major equipment manufacturer – designed to gain the edge on their competitors, dream up a sales gimmick feature? A cheaper option to buying two units – one acting as a standby for the other in case it failed, was to simply duplicate the components that could cause the unit to fail e.g. the fan or a fan belt.

The power surge from the electrical supply authority’s main was soaked up by the UPS and the computer equipment is unaffected and continues running– until the room temperature rises to the set level that switches it off – hopefully before it cooks itself!
To find out what it’s all about and how to avoid – appoint CCS

The showers
Split system cassettes or wall mounted air handling units are often installed in such a way as to shower the rooms beneath with water. Not the best conditions for your Computer server/Telecoms room!
To find out what it’s all about and how to avoid – appoint CCS

No blow?
The fan coil units are not circulating conditioned air, in fact, little air at all. The fans are rotating and the condensers appear to be operating satisfactorily.
To find out what it’s all about and how to avoid – appoint CCS

Melting ceiling tiles?
The suspended ceiling tiles apparently melt and drip on to whatever is beneath – somebody’s law determines it will be your main server – or most sensitive member of staff!
To find out what it’s all about and how to avoid – appoint CCS

Bring down the ceiling?
The computer room floor void is insufficient to carry both computer cables and leave sufficient free space for conditioned air supply. The answer was to deliver conditioned air via slotted metal ceiling tiles into the room and collect it in the front panels of the room mounted air handling units. When the air conditioning is turned on, part of the suspended ceiling falls to the floor!
To find out what it’s all about and how to avoid – appoint CCS

The black room!
The computer room air conditioning contains high efficiency filtration. Yes, the fresh air is entrained before the filters. Conditioned air is introduced into the room through the ceiling void, via perforated ceiling tiles because of a lack of floor void depth available. The ceiling tiles quickly change colour from white to black. The computer equipment surfaces begin to darken. The computer manufacturers’ engineers begin issuing their helpful disclaimers…
To find out what it’s all about and how to avoid – appoint CCS

The plunge-pool mentality
The comfort conditioning system comprises groups of ceiling mounted cassettes serving the open-plan office area. It is controlled via wall mounted controllers from which temperature and fan speed may be set. The system has capacity to maintain temperatures of circa 70/72 degrees C when temperatures outside the premises are as low as -5 degrees C and as high as 30 degrees C. Once the external temperatures are exceeded the system will lag circa 5 degrees behind – normal design conditions.

At the start of the working day conditions in the space are fine. After lunch, chaos reigns:

In the summer staff complain that the room is too warm – usually when it's hot outside. They claim the conditioning system is not working properly.

In the winter they complain that the room is too cool. Temperature reading in room shows them to be lower than the normal set point when the summer complaints are made and warmer than the norm in the winter!
To find out what it’s all about and how to avoid – appoint CCS

Star Wars!
The open plan office is cooled by means of a number of high wall mounted split system fan coil units. Adjustment of the units is provided by means of hand-held infrared controllers.
Complaints are continually received that some of the units are not cooling, are leaking and blowing out warm air.

Checks are carried out: The refrigeration pipework for leaks, filters checked for clarity and the infrared controllers' settings. What is the source of the problem?
To find out what it’s all about and how to avoid – appoint CCS

High wall mounted block of ice!
An office split system unit high wall mounted unit keeps leaking. In fact it is freezing up. The filter is clean, the refrigeration pressure and content correct. What is wrong?
To find out what it’s all about and how to avoid – appoint CCS

Turn off
The comfort conditioning system suspended ceiling mounted cassette units have been installed for a few weeks, when complaints are received that they no longer appear to be controlling the room temperature.

The controls and refrigeration circuits are all checked and found to be fine. When one of the filter banks is removed from a cassette unit, it resembles a sheet of cardboard!
To find out what it’s all about and how to avoid – appoint CCS

For ever, and ever, and ever
The computer room is constructed within a huge, brand new, office/shopping mall complex. The fabric comprises thick, solid, reinforced concrete walls, floor and ceiling. It is absolutely ideal for a secure facility.

Following the fitting-out, the air conditioning is turned on and tested before the computer equipment is installed.

It doesn’t work! It can’t control the temperature! It can’t even raise the room to its 22 degrees set point – let alone cool it!

The systems are thoroughly checked out and all components, and their design, are fine. It is left running for a week – to settle down, but still will not control the temperature. And another week, and another, and another! … What was wrong?
To find out what it’s all about and how to avoid – appoint CCS

Lonely
The large computer room is completed and all the services, including the air conditioning system, have been tested and commissioned - without any problems having been found.
A simulated heat load test is carried out to check that the air conditioning is able to cope with the anticipated computer equipment load.

A few items of mainframe computer equipment are installed and commissioned.

The air conditioning cannot control the room temperature! The isometric chart sketches out what resembles the profile of a crosscut circular saw blade. Engineers and designers return, but all checks out O.K. The computer manufacturers begin issuing their disclaimers…
To find out what it’s all about and how to avoid – appoint CCS

Electrical Services

The alternative bypass switch
The UPS equipment regularly switches into bypass in the summer months due to overheating. A large fresh air fan that is apparently working correctly and was not a problem during the previous summer – when external temperatures were higher, ventilates the room. There is nothing else outside, or in, that could be an additional heat source – yes the fan was rotating!
To find out what it’s all about and how to avoid – appoint CCS

Hello, hello?
The server/telecoms room is UPS supported. The UPS has its own standby generator support in case of a mains power failure.

The premises telephone switchboard equipment has its own UPS battery pack – a safeguard because if power to it is lost then its software has to be reloaded – at the usual sky-high engineer’s time and call-out cost.

The mains fail, the UPSs take over, the generator takes over.

A couple of hours later, the computer manager calls his boss(director actually!) to reassure him that all is under control. As he is speaking the line goes dead – as do all those in the building - and they stay down!
To find out what it’s all about and how to avoid – appoint CCS

Fault loose
The mainframe item of computer equipment has an intermittent fault. The computer engineer denies it. The electrical supply quality is checked and found to be fine. The commando socket/termination box connections are checked – all O.K. The breaker is correctly sized and of the correct type. So what was wrong?
To find out what it’s all about and how to avoid – appoint CCS

UPS and out!
There is a mains power failure. The UPS takes over. There is no standby generator, but the computer operators use the few minutes the UPS gives them to backup files and then shut down the computer system – which is one reason for having the UPS.

The power returns, everything restarts – and the main breaker blows – unfortunately by now the UPS batteries are fully discharged from the previous exercise!
To find out what it’s all about and how to avoid – appoint CCS

The lazy generator
The standby generator – which fails to start when the mains power disappears in the winter, faithfully starts every time on test during the summer!
To find out what’s it all about and to avoid similar– Appoint CCS

The dead generator
Despite regular testing, one day nothing happens when the standby generator auto start switch is engaged by a mains failure!
To find out what’s it all about and to avoid similar– Appoint CCS

No fuel!
The standby diesel generator housing stands on the other side of a fence to a petrol station – yes it does sell the type of diesel oil used by the generator!

Someone had decided that spare space was at a premium and that a large fuel tank was not needed for the generator – 4 hours run time would be sufficient, after that someone would have to pop across to the fuel station with a Gerry can for a refill.

It was only when there was a mains failure that lasted for more than four hours that the major flaw in their plans dawned!
To find out what it’s all about and how to avoid – appoint CCS

Security Systems

Barafoam saga continues
A carbon dioxide full flood extinguishing system is installed to fill the large ducts lined with the errant foam.

The ducts lead from the ground floor central air conditioning plant and feed into the first floor raised modular floor void of the computer room above.

The 12 large bottles of CO2 gas are stored on the ground floor. The gas, is to be held inside When it is injected, the gas is to be retained in the ducts by large, steel plate, 2hr fire resistant dampers.

Motors and gearing arrangements are fitted to the dampers to close them. They are battery operated because in the event of a fire alarm, the mains electrical supply is isolated.

Trials are carried out and the motors are unable to deal with the weight of the dampers. Modifications are carried out and the underwriters advised.

They wish to witness a live test of the gas flooding system before they are willing to accept the risk.

They are due to arrive from London at circa midday and so the damper closing tests are carried out continually during the morning.

The sequence for the test is:

1. The fire alarm is activated by the site engineer from a manual break glass unit in the viewing gallery overlooking the computer room.
2. The alarms sound for a pre-set period.
3. The sound of the dampers closing echoes around the room.
4. The carbon dioxide is injected into the ducts.

The raised flooring above the ducts is removed to enable the witnesses to the view the dampers and their sealing effect – in containing the gas.

A dozen underwriters solemnly arrive for the test and stand around the large openings in the raised floor.

The site engineer activates the manual release button.

The alarms sound and the damper release timer commences.

There is no sound echoing around the room! The dampers do not close!

There is no time to warn the witnesses! The gas is released!

A dozen underwriters disappear from view in a cloud of carbon dioxide!

The site engineer begins to compose his letter of resignation, witness report to the police.
To find out what it’s all about and how to avoid – appoint CCS

Fire!
The alarms of the fire detection devices in the remote room/site are connected by means of an auto dialler to the 24/7 operations office telephone. The fire brigade are brushing away water and ashes before your operations staff find out about the fire!
To find out what it’s all about and how to avoid – appoint CCS

Thank you!
The office suites are protected by means of an iris-reading access control system – correctly installed and approved by all – including the fire officer. The following day everyone evacuates the premises - and thieves rush in and remove all your laptop computers! The insurance company explains why your claim for compensation will not be met!
To find out what it’s all about and how to avoid – appoint CCS

Al Reid Show?
In the event of the HSSD system detecting a fire in your computer room whilst the premises is unoccupied apart from your security staff, the security officer on duty will locate the source of the fire condition, switch off the offending device and attack any fire with one of the Inergen gas hand-held fire extinguishers available throughout the premises. Should the fire be more than he is able to control he will call the fire brigade and one of the operations staff.

The telecoms/server cabinet is a pile of ash by the time the fire brigade arrive – and flood your room with water.
To find out what it’s all about and how to avoid – appoint CCS

Hi There!
The person who stole the externally mounted CCTV surveillance camera was caught on video. He was wearing a black tracksuit and a balaclava. He was described as having a fine set of teeth – also captured on film, as he smiled for the camera – before the picture disappeared as he cut the cables to release and steal it!
To find out what it’s all about and how to avoid – appoint CCS

Building Items

The squeeze
The new owners of a new company decided that a fresh image was required. They decided that the business ought to relocate from the Victorian rambling mansion, converted garage and prefabricated unit, to a modern office block.

One of their directors took up the mantle. He measured the existing accommodation floor area and found a new office development in the locale that seemed to suit the bill. However…

New furniture had to be purchased to enable all the workstation positions to fit into the new premises and one department found itself split between floors and demanded meeting rooms to compensate – but there was no space for them.

The outcome of the exercise was that the company had to take on another office building on the estate – and attempt to let out a half of it – because now they had too much space!
To find out what it’s all about and how to avoid – appoint CCS

Candyfloss syndrome
The computer room is huge and has only been commissioned and handed over a few months ago– by the largest contracting organisation in the UK. However, when the computer operators exit the computer room, they appear more hirsute than when they entered! When they lower the glass screen on the tape drives, the tapes are seen to be covered in hair! The computer engineers issue their usual helpful punitive threats and disclaimers regarding the environment…
To find out what it’s all about and how to avoid – appoint CCS

Window radiators
The contractors have applied the solar reflective film to the double glazed windows - to reduce heat gains in your special areas. However some of the double glazed units have since cracked and the room’s cooling system doesn’t appear to be able to cope - when the sun is shining. The mechanical services engineer has checked his equipment and calculations. The staff complains about the heat, the equipment protests by switching itself off….
To find out what it’s all about and how to avoid – appoint CCS

Door slammers
The door closers are fitted to all doors and checked for adjustment before the site is handed over to you. You occupy, and the all the doors slam closed. Personnel complain, have fingers removed, or suffer shock. Further adjustment of the closers has little effect.
To find out what it’s all about and how to avoid – appoint CCS

Raised modular abstract art?
The client was a large financial institution and they built a new headquarters premises and a showpiece computer room. Their Architect insisted that he could handle the computer room fabric – didn’t need consultants for that!

Relevant information was sent to him and he placed orders and managed the works.
He insisted that the raised floor had to be covered in carpet containing the client corporate colours – grey and blue – which was only reasonable.

He then had the bright idea of having the initial letters of the institution formed on the raised floor surface by having an appropriate mix of blue and grey tiles. This was quite an exercise, because some tiles needed to have a shaped insert forming the edges of the blue letters on a grey background. Templates were drawn up and sent to the factory where the carpet tiles had to be specially cut – to the fine tolerances required (which is why loose laid are used wherever possible on floors where access is not required).

The floor was laid with the four large initial letters proudly displayed for all to see from the visitors’ gallery overlooking the computer room.

Unfortunately the two essential activities that immediately followed reduced the lettering to a visual shambles and the coloured tiles were eventually replaced!
To find out what it’s all about and how to avoid – appoint CCS

Nice pedestals!
The raised floor had been installed and computer equipment moved into the new room. As the fire safe was wheeled in some floor tiles sank as it passed over them, others remained unaffected – small comfort! The occupants of the office on the floor below note pedestals protruding through their ceiling!
To find out what it’s all about and how to avoid – appoint CCS

Raised inaccessible floor
Following the installation of the raised floor, comprising 600 x 600mm loose-laid panels supported upon pedestals, in the new telecoms room, the builder then laid the 500 x 500mm carpet tiles over – staggered in the specified manner – so as to avoid panel and carpet tile joints coinciding.

The telecoms equipment and communications racks were then positioned in the room. When the electrician and cabling contractors arrived to lay their cables beneath the floor, the builder had to be called back to cut holes through it for access!
To find out what it’s all about and how to avoid – appoint CCS

Raised access carpet
The builder is asked to provide a raised modular floor. The product supplied has a bare sheet steel finish – not best for a computer room! He is instructed that the floor panels are to be finished with carpet bonded to them. The replacement product seems fine – until a floor tile is lifted and while the carpet adheres to the lifting device, the floor panel returns to base - at 32ft per sec2!
To find out what it’s all about and how to avoid – appoint CCS

Window streams
The extension to contain the new computer room had been completed. The windows, galvanised framed to match existing - were double-glazed and the walls and floor suitably insulated. There was a vapour seal built into the roof fabric.

The air conditioning was installed, commissioned and left running over the weekend – to settle down.

On Monday morning the room floor void was found to be flooded to a depth of 50mm.
To find out what it’s all about and how to avoid – appoint CCS

Stolen Back fill?
It is the beginning of the spring season. The drains connecting the new building to the main sewer, had been laid, tested and their trench backfilled - before the builder left site weeks before – when winter was still around and snow was on the ground.

You look out of the window and notice that someone has apparently dug out the trenches again!
To find out what it’s all about and how to avoid – appoint CCS

Showers 2
You move into the new premises which is in the middle of a large estate. It comprises a large industrial unit containing offices, a hi-tech manufacturing facility on the warehouse floor and associated stores.

The premises frame is a double span of steel portals. A valley gutter runs the length of the building – between the portals.

The gutters are cleaned and inspected before you move in.
Two months later the gutter leaks. Inspection reveals that it is blocked – what with?
To find out what it’s all about and how to avoid – appoint CCS

Showers 3
Scene: The same premises as in showers 2.

The valley gutter is checked once every month. Special note is made to ensure that the symphonic drain outlets and the perimeter roof gutter overflows are clear.

A downpour occurs and thousands of gallons of water spray from the underside of the valley gutter edges – inside the premises, flooding the whole of the warehouse area to a depth of several inches! Damage is estimated in £millions!
To find out what it’s all about and how to avoid – appoint CCS

Paddling facility
Scene: The same site!

Apart from the drains problems, when there is a downpour, most of the estate floods – to a depth of a few inches, some of which find its way into the manufacturing and R&D areas.
The meteorological office is contacted to find out whether they have recorded unusually high levels of rainfall in the area. They have no such records.

The local Planning and Rivers Authorities are contacted and asked what they intend doing about the flooding. They will do nothing.

Going, going…
The client was a Regional Authority. The new first floor computer room had been constructed and commissioned. All that remained was for the mainframe computer processor to be delivered and installed.

The chairman of the project progress meeting thanked us for our efforts but felt that the Authority could at least handle the delivery of the processor. He asked their site maintenance engineer to arrange the erection of the scaffolding platform to the first floor window of the new computer room and for a small crane to lift the computer onto the platform.

The crane lifted the computer onto the scaffolding platform – which slowly toppled over and returned the mainframe to ground level!
To find out what it’s all about and how to avoid – appoint CCS

Moles?
Computer room raised modular floor tiles were originally constructed from plywood. A less expensive alternative was discovered when chipboard was introduced.

The first of these floors was installed in a newly constructed computer room in London. The room was commissioned, tested and handed over to the client.

It was just a few days before the complaints about bumps appearing in the surface of the floor were raised!
To find out what it’s all about and how to avoid – appoint CCS

Click here to email us
Click here to contact us by telephone
Click here to contact us by post
Click here for our advice center
Call 01938 552 975    Email ccs@computer-rooms.com  
Request A Quote